By the end of 2024, site clearance will be completed to serve the construction of National Highway 14B
On October 1, the People’s Committee of Hoa Vang City (Da Nang City) launched a 90-day “campaign” to complete site clearance for the construction of the project to renovate and upgrade National Highway 14B.
Like Adolescent It was announced that the project to renovate and upgrade Highway 14B section through Da Nang City will start construction at the end of November 2023, 7.58 km long, from the La Son – Tuy Loan expressway intersection (Hoa Nhon commune) to Hoa Khuong commune (Hoa Khuong commune) bordering Quang Nam) with a total investment of more than 788 billion VND.
The People’s Committee of Da Nang City assigned the Department of Transport of Da Nang City to be the investor, and the People’s Committee of Hoa Vang City to carry out compensation and site clearance.
Mr. Nguyen Thuc Dung, Standing Vice Chairman of Hoa Vang People’s Committee, said that in order for the project to have a construction site and ensure completion by the end of 2025, the entire political system needs to participate with great efforts. , high determination. The entire route has 1,075 land parcel documents of more than 800 households that must be recovered. Up to now, 1,050 documents have been inventoried and compensation documents, 980 documents have been held for legal review, prices have been applied and a decision has been issued. Approved the compensation value of 902 documents, paid and handed over the premises of 342 documents.
“However, the site clearance work for the National Highway 14B project has many difficulties and complications. The agencies have to work and review the difficulties, make legitimate and appropriate recommendations, and at the same time propose the City People’s Committee to agree agree on a compensation and resettlement plan to ensure people’s rights,” said Mr. Nguyen Thuc Dung.
On October 1, the People’s Committee of Hoa Vang District launched a determined emulation movement of 90 days and nights to complete site clearance by the end of 2024. “With the spirit of striving and high determination, not afraid of difficulties or suffering, doing all the work, not running out of hours, not including Saturdays and Sundays, not doing enough during the day, taking advantage of the work at night, with the method “Clear people, clear tasks, clear responsibilities, clear progress, clear effectiveness, discuss work, don’t talk back, once done, it must be done,” said Mr. Nguyen Thuc Dung.
For the three communes of Hoa Khuong, Hoa Phong, Hoa Nhon located on National Highway 14B passing through, policies on land acquisition, compensation, support, and resettlement must be made public. Working groups must promptly explain the policies so that people The people agreed and mobilized cadres and party members to be exemplary pioneers.
Ensuring people’s lives are equal to or better than their old residence
In the next 90 days, the People’s Committee of Hoa Vang District directs specialized agencies to carefully review the legal system, complete errors, proactively advise on removing difficulties, and soon complete the records of each household, on a timely basis. The people will have a new place to live, ensuring a life equal to or better than the old place.
Hoa Vang H. People’s Committee also requested the Department of Transport and contractors to focus on human resources and vehicles to speed up the construction progress as soon as the site is handed over.
Mr. Le Trung Chinh, Chairman of the People’s Committee of Da Nang City, said that the project to renovate and upgrade National Highway 14B through Da Nang City is a project of strategic significance in perfecting the road traffic infrastructure system. not only of Da Nang, but of the whole country, forming a horizontal axis connecting the western traffic axes of Ho Chi Minh Highway with the North-South expressway axes and National Highway 1 in the East, connecting the East-West Economic Corridor 2, making an important contribution to promoting socio-economic development of localities along the route.
The completed project also contributes to changing the appearance of the western gateway of Da Nang City in a modern direction, creating new space for urban development to the west following the development orientation of Da Nang City, at the same time. The project has important significance for the development of Hoa Vang District into a grade 4 urban area, becoming a town.